HOUSE BILL No. 5051

 

July 24, 2007, Introduced by Reps. Stakoe, Meekhof, Ball, Hammon, Caul, Robertson, Hansen, Nofs and Caswell and referred to the Committee on Oversight and Investigations.

 

      A bill to amend 1980 PA 497, entitled

 

"Construction lien act,"

 

by amending sections 107, 108a, 109, 110, 115, 119, and 203 (MCL

 

570.1107, 570.1108a, 570.1109, 570.1110, 570.1115, 570.1119, and

 

570.1203), section 107 as amended by 2006 PA 497, section 108a as

 

added and sections 109 and 119 as amended by 1982 PA 17, and

 

sections 110, 115, and 203 as amended by 2006 PA 572.

 

THE PEOPLE OF THE STATE OF MICHIGAN ENACT:

 

 1        Sec. 107. (1) Each Subject to subsection (7), each

 

 2  contractor, subcontractor, supplier, or laborer who provides an

 

 3  improvement to real property has a construction lien upon the

 

 4  interest of the owner or lessee who contracted for the

 

 5  improvement to the real property, as described in the notice of


 

 1  commencement given under section 108 or 108a, the interest of an

 

 2  owner who has subordinated his or her interest to the mortgage

 

 3  for the improvement of the real property, and the interest of an

 

 4  owner who has required the improvement. A construction lien

 

 5  acquired pursuant to this act shall not exceed the amount of the

 

 6  lien claimant's contract less payments made on the contract.

 

 7        (2) A construction lien under this act attaches to the

 

 8  entire interest of the owner or lessee who contracted for the

 

 9  improvement, including any subsequently acquired legal or

 

10  equitable interest.

 

11        (3) Each Subject to subsection (7), each contractor,

 

12  subcontractor, supplier, or laborer who provides an improvement

 

13  to real property to which the person contracting for the

 

14  improvement had no legal title has a construction lien upon the

 

15  improvement for which the contractor, subcontractor, supplier, or

 

16  laborer provided labor, material, or equipment. The forfeiture,

 

17  surrender, or termination of any title or interest held by an

 

18  owner or lessee who contracted for an improvement to the

 

19  property, an owner who subordinated his or her interest to the

 

20  mortgage for the improvement, or an owner who has required the

 

21  improvement does not defeat the lien of the contractor,

 

22  subcontractor, supplier, or laborer upon the improvement.

 

23        (4) If the rights of a person contracting for an improvement

 

24  as a land contract vendee or a lessee are forfeited, surrendered,

 

25  or otherwise terminated, any lien claimant who has provided a

 

26  notice of furnishing or is excused from providing a notice of

 

27  furnishing under section 108 , 108a, or 109 and who performs the


 

 1  covenants contained in the land contract or lease within 30 days

 

 2  after receiving actual notice of the forfeiture, surrender, or

 

 3  termination is subrogated to the rights of the contracting vendee

 

 4  or lessee as those rights existed immediately before the

 

 5  forfeiture, surrender, or termination.

 

 6        (5) For purposes of this act, if the real property is owned

 

 7  or leased by more than 1 person, there is a rebuttable

 

 8  presumption that an improvement to real property under a contract

 

 9  with an owner or lessee was consented to by any other co-owner or

 

10  co-lessee. If enforcement of a construction lien through

 

11  foreclosure is sought and the court finds that the improvement

 

12  was consented to by a co-owner or co-lessee who did not contract

 

13  for the improvement, the court shall order the entire interest of

 

14  that co-owner or co-lessee, including any subsequently acquired

 

15  legal or equitable interest, to be subject to the construction

 

16  lien. A deficiency judgment shall not be entered against a

 

17  noncontracting owner, co-owner, lessee, or co-lessee.

 

18        (6) If the real property of an owner or lessee is subject to

 

19  multiple construction liens, the sum of the construction liens

 

20  shall not exceed the amount the owner or lessee agreed to pay the

 

21  person with whom he or she contracted for the improvement as

 

22  modified by all additions, deletions, and other amendments, less

 

23  payments made by or on behalf of the owner or lessee, pursuant to

 

24  either a contractor's sworn statement or a waiver of lien, in

 

25  accordance with this act.

 

26        (7) After the effective date of the amendatory act that

 

27  added this subsection, a construction lien of a subcontractor or


 

 1  supplier for an improvement to a residential structure shall only

 

 2  include an amount for interest, including, but not limited to, a

 

 3  time-price differential or a finance charge, if the amount is in

 

 4  accordance with the terms of the contract between the

 

 5  subcontractor or supplier and the contractor or subcontractor and

 

 6  does not include any interest that accrues after 90 days after

 

 7  the claim of lien is recorded.

 

 8        (7) A subcontractor, supplier, or laborer is not entitled to

 

 9  a construction lien on a residential structure.

 

10        Sec. 108a. (1) An owner or lessee contracting for an

 

11  improvement to a residential structure shall prepare and provide

 

12  a notice of commencement to a contractor , subcontractor,

 

13  supplier, or laborer who has made a written request for the

 

14  notice pursuant to this section.

 

15        (2) The notice of commencement shall contain the following

 

16  information:

 

17        (a) The legal description of the real property on which the

 

18  improvement is to be made. A description conforming to section

 

19  212 or 255 of Act No. 288 of the Public Acts of 1967, being

 

20  sections 560.212 and 560.255 of the Michigan Compiled Laws, shall

 

21  be the land division act, 1967 PA 288, MCL 560.212 and 560.255,

 

22  is a sufficient legal description.

 

23        (b) The name, address, and capacity of the owner or lessee

 

24  of the real property contracting for the improvement.

 

25        (c) The name and address of the fee owner of the real

 

26  property, if the person contracting for the improvement is a land

 

27  contract vendee or lessee.


 

 1        (d) The name and address of the owner's or lessee's

 

 2  designee.

 

 3        (e) The name and address of the general contractor, if any.

 

 4  The notice of commencement form shall contain the following

 

 5  caption below the line for the general contractor's name and

 

 6  address: (the name of the person with whom you have contracted to

 

 7  provide substantially all the improvements to the property.)

 

 8        (e) (f) The following statement in boldface type on the

 

 9  front of the form:

 

10                       WARNING TO HOMEOWNER

 

11        Michigan law requires that you do the following:

 

12        1. Complete and return this form to the person a contractor

 

13  who asked for requests it within 10 days after the date of the

 

14  postmark on the request.

 

15        2. If you do not complete and return this form within the 10

 

16  days you may have to pay the expenses incurred in getting the

 

17  information.

 

18        3. If you do not live at the site of the improvement, you

 

19  must post a copy of this form in a conspicuous place at that

 

20  site.

 

21        You are not required to but should do the following:

 

22        1. Complete and post a copy of this form at the place where

 

23  the improvement is being made, even if you live there.

 

24        2. Make and keep a copy of this form for your own records.

 

25        (f) (g) The following statement:

 

26        "To lien claimants and subsequent purchasers:

 

27        Take notice that work is about to commence on an improvement


 

 1  to the real property described in this instrument. A person

 

 2  contractor having a construction lien may preserve the lien by

 

 3  providing a notice of furnishing to the above named designee and

 

 4  the general contractor, if any, and by timely recording a claim

 

 5  of lien, in accordance with law.

 

 6        A person contractor having a construction lien arising by

 

 7  virtue of work performed on this improvement should refer to the

 

 8  name of the owner or lessee and the legal description appearing

 

 9  in this notice. A person subsequently acquiring an interest in

 

10  the land described is not required to be named in a claim of

 

11  lien.

 

12        A copy of this notice with an attached form for notice of

 

13  furnishing may be obtained upon making a written request by

 

14  certified mail to the above named owner or lessee ; or the

 

15  designee." ; or the person with whom you have contracted."

 

16        (g) (h) The name and address of the person preparing the

 

17  notice.

 

18        (h) (i) An affidavit of the owner or lessee or the agent of

 

19  the owner or lessee which that verifies the notice.

 

20        (3) Each copy of the notice of commencement shall have a

 

21  blank notice of furnishing as described in section 109 attached

 

22  to it. The blank notice of furnishing shall be easily detachable

 

23  from the copy of the notice and need not be recorded.

 

24        (3) (4) Incorrect information contained in the notice of

 

25  commencement furnished by or for an owner or lessee shall does

 

26  not affect adversely the rights of a lien claimant as against the

 

27  property of that owner or lessee.


 

 1        (4) (5) The owner, lessee, or designee, within 10 days after

 

 2  the date of mailing of a written request by certified mail from a

 

 3  contractor, subcontractor, supplier, or laborer, shall prepare

 

 4  and provide a copy of the notice of commencement , together with

 

 5  an attached blank notice of furnishing form, to the contractor. ,

 

 6  subcontractor, supplier, or laborer requesting a copy of the

 

 7  notice of commencement. A contractor , subcontractor, supplier,

 

 8  or laborer who requests a notice of commencement from an owner or

 

 9  lessee of a residential structure shall supply a blank notice of

 

10  commencement form together with the attached blank notice of

 

11  furnishing to the owner or lessee at the time the request is

 

12  made.

 

13        (6) A contractor who has been provided with a notice of

 

14  commencement from the owner, lessee, or designee, within 10 days

 

15  after the date of mailing of a written request by certified mail

 

16  from a subcontractor, supplier, or laborer who has a direct

 

17  contract with the contractor, shall provide a copy of the notice

 

18  of commencement, together with an attached blank notice of

 

19  furnishing form, to the subcontractor, supplier, or laborer

 

20  requesting a copy of the notice of commencement. If the

 

21  contractor has not been provided a notice of commencement, the

 

22  contractor shall provide such subcontractor, supplier, or laborer

 

23  the name and address of the owner or lessee.

 

24        (7) A subcontractor who has been provided with a notice of

 

25  commencement from the owner, lessee, designee, contractor, or

 

26  subcontractor, within 10 days after the date of mailing of a

 

27  written request by certified mail from a subcontractor, supplier,


 

 1  or laborer who has a direct contract with the subcontractor,

 

 2  shall provide a copy of the notice of commencement, together with

 

 3  an attached blank notice of furnishing form, to the

 

 4  subcontractor, supplier, or laborer requesting a copy of the

 

 5  notice of commencement. If the subcontractor has not been

 

 6  provided a notice of commencement, the subcontractor shall

 

 7  provide to such subcontractor, supplier, or laborer, the name and

 

 8  address of the owner or lessee.

 

 9        (5) (8) If the owner, lessee, or designee has received a

 

10  blank notice of commencement form pursuant to subsection (5) (4)

 

11  and if the owner or lessee does not currently reside at the real

 

12  property described in the notice of commencement, the owner,

 

13  lessee, or designee shall post a copy of the notice of

 

14  commencement in a conspicuous place on the real property during

 

15  the course of the actual physical improvement to the real

 

16  property.

 

17        (9) Failure of the owner, lessee, or designee to provide,

 

18  upon written request, the notice of commencement, in accordance

 

19  with this section, shall operate to extend the time within which

 

20  a subcontractor or supplier may provide a notice of furnishing,

 

21  as described in section 109, until 20 days after the notice of

 

22  commencement actually has been furnished to the subcontractor or

 

23  laborer.

 

24        (10) Failure of the owner, lessee, or designee to provide

 

25  the notice of commencement, in accordance with this section,

 

26  shall operate to extend the time within which a laborer may

 

27  provide a notice of furnishing, as described in section 109,


 

 1  until 30 days after the notice of commencement actually has been

 

 2  furnished to the laborer, or until the time in which to provide

 

 3  the notice of furnishing in accordance with section 109 expires,

 

 4  whichever is later.

 

 5        (11) Failure of the owner, lessee, or designee to post or

 

 6  keep posted a copy of the notice of commencement as provided in

 

 7  subsection (8) shall render the owner or lessee liable to a

 

 8  subcontractor, supplier, or laborer who becomes a lien claimant

 

 9  for all actual expenses sustained by the lien claimant in

 

10  obtaining the information otherwise provided by the posting.

 

11        (12) Failure of a contractor, who has been provided with a

 

12  notice of commencement from the owner, lessee, or designee, to

 

13  provide the notice of commencement upon the request of a lien

 

14  claimant who has a contract with the contractor for an

 

15  improvement to the property shall render the contractor liable to

 

16  the lien claimant for all actual expenses sustained by the lien

 

17  claimant in obtaining the information otherwise provided by the

 

18  notice of commencement. Failure of a contractor to provide the

 

19  name and address of the owner or lessee in accordance with

 

20  subsection (6) shall render the contractor liable to the lien

 

21  claimant for all actual expenses sustained by the lien claimant

 

22  in obtaining the name and address of the owner or lessee.

 

23        (13) Failure of a subcontractor, who has been provided with

 

24  a notice of commencement from the owner, lessee, designee,

 

25  contractor, or subcontractor, to provide the notice of

 

26  commencement upon the request of a subcontractor, supplier, or

 

27  laborer who has a direct contract with the subcontractor shall


 

 1  render the subcontractor liable to such subcontractor, supplier,

 

 2  or laborer for all actual expenses sustained by the

 

 3  subcontractor, supplier, or laborer in obtaining the information

 

 4  otherwise provided by the notice of commencement. Failure of a

 

 5  subcontractor to provide the name and address of the owner or

 

 6  lessee in accordance with subsection (6) shall render the

 

 7  subcontractor liable to the lien claimant for all actual expenses

 

 8  sustained by the lien claimant in obtaining the name and address

 

 9  of the owner or lessee.

 

10        (6) (14) This section shall only apply applies to an

 

11  improvement to a residential structure.

 

12        Sec. 109. (1) Except as otherwise provided in sections 108 ,

 

13  108a, and 301, a subcontractor or supplier who contracts to

 

14  provide an improvement to real property other than a residential

 

15  structure shall provide a notice of furnishing to the designee

 

16  and the general contractor, if any, as named in the notice of

 

17  commencement at the address shown in the notice of commencement,

 

18  either personally or by certified mail, within 20 days after

 

19  furnishing the first labor or material. If a designee has not

 

20  been named in the notice of commencement, or if the designee has

 

21  died, service shall be made upon the owner or lessee named in the

 

22  notice of commencement. If service of the notice of furnishing is

 

23  made by certified mail, service is complete upon mailing. A

 

24  contractor is not required to provide a notice of furnishing to

 

25  preserve lien rights arising from his or her contract directly

 

26  with an owner or lessee.

 

27        (2) Except as otherwise provided in sections section 108,


 

 1  and 108a, a laborer who contracts to provide an improvement to

 

 2  real property other than a residential structure shall provide a

 

 3  notice of furnishing to the designee and the general contractor,

 

 4  if any, as named in the notice of commencement at the address

 

 5  shown in the notice of commencement, either personally or by

 

 6  mail, within 30 days after wages were contractually due but were

 

 7  not paid. If a designee has not been named in the notice of

 

 8  commencement, or if the designee has died, service shall be made

 

 9  upon the owner or lessee named in the notice of commencement. If

 

10  service of the notice of furnishing is made by mail, service is

 

11  complete upon mailing by first class mail with postage prepaid.

 

12        (3) Except as otherwise provided in sections section 108,

 

13  and 108a, a laborer who provides an improvement to real property

 

14  other than a residential structure shall provide a notice of

 

15  furnishing to the designee and the general contractor, if any,

 

16  named in the notice of commencement at the address shown in the

 

17  notice of commencement, either personally or by certified mail,

 

18  by the fifth day of the second month following the month in which

 

19  fringe benefits or withholdings from wages were contractually due

 

20  but were not paid. If a designee has not been named in the notice

 

21  of commencement, or if the designee has died, service shall be

 

22  made upon the owner or lessee named in the notice of

 

23  commencement. If service of the notice of furnishing is made by

 

24  certified mail, service is complete upon mailing.

 

25        (4) The notice of furnishing, if not given on the form

 

26  attached to the notice of commencement, shall be in substantially

 

27  the following form:


 

 

                        NOTICE OF FURNISHING

To: ...............................................................

(name of designee (or owner or lessee) from notice of commencement)

    ...............................................................

                 (address from notice of commencement)

Please take notice that the undersigned is furnishing to ..........

...................................................................

               (name and address of other contracting party)

certain labor or material for ................................... ,

10                                       (describe type of work)

11 in connection with the improvements to the real property described

12 in the notice of commencement recorded in liber .............. , on

13 page ...... , .............................................records,

14                               (name of county)

15 ................................................................. .

16                 or (a copy of which is attached hereto)

17      WARNING TO OWNER: THIS NOTICE IS REQUIRED BY THE MICHIGAN

18 CONSTRUCTION LIEN ACT. IF YOU HAVE QUESTIONS ABOUT YOUR RIGHTS

19 AND DUTIES UNDER THIS ACT, YOU SHOULD CONTACT AN ATTORNEY TO

20 PROTECT YOU FROM THE POSSIBILITY OF PAYING TWICE FOR THE

21 IMPROVEMENTS TO YOUR PROPERTY.

22                              ......................................

23                                (name and address of lien claimant)

24                              by ...................................

25                                    (name and capacity of party

26                                     signing for lien claimant)

27                              ......................................

28                                    (address of party signing)

29 Date: ...................... .

 

 

30        (5) The failure of a lien claimant to provide a notice of

 

31  furnishing within the time specified in this section shall does

 

32  not defeat the lien claimant's right to a construction lien for

 

33  work performed or materials furnished by the lien claimant after


 

 1  the service of the notice of furnishing.

 

 2        (6) The failure of a lien claimant , to provide a notice of

 

 3  furnishing within the time specified in this section shall does

 

 4  not defeat the lien claimant's right to a construction lien for

 

 5  work performed or materials furnished by the lien claimant before

 

 6  the service of the notice of furnishing except to the extent that

 

 7  payments were made by or on behalf of the owner or lessee to the

 

 8  contractor pursuant to either a contractor's sworn statement or a

 

 9  waiver of lien in accordance with this act for work performed or

 

10  material delivered by the lien claimant. This subsection does not

 

11  apply to a laborer.

 

12        (7) The failure of a laborer to provide a notice of

 

13  furnishing to the designee as required by subsection (2) shall

 

14  defeat defeats the laborer's lien for those wages for which the

 

15  notice of furnishing is required.

 

16        (8) The failure of a laborer to provide a notice of

 

17  furnishing to the designee as required by subsection (3) shall

 

18  defeat defeats the laborer's lien for those fringe benefits and

 

19  withholdings for which the notice of furnishing is required.

 

20        (9) The failure of a laborer to provide a notice of

 

21  furnishing to the general contractor within the time specified in

 

22  subsection (2) or (3) shall does not defeat the laborer's right

 

23  to a construction lien, but the laborer shall be is liable for

 

24  any actual damages sustained by the general contractor as a

 

25  result of the failure.

 

26        (10) One or more laborers may authorize an agent to prepare

 

27  and serve a notice of furnishing in the manner provided in this


 

 1  section. Notice A notice of furnishing under this section may

 

 2  contain the notice of furnishing of more than 1 laborer, and in

 

 3  which case it shall contain the information required in

 

 4  susbsection subsection (4) as to each laborer for whom it is

 

 5  prepared. The court shall consider the notice of furnishing of

 

 6  each lien claimant under this subsection shall be considered by

 

 7  the court on its own merits.

 

 8        (11) This section does not apply if the real estate involved

 

 9  is a residential structure. A subcontractor, laborer, or supplier

 

10  shall not provide a notice of furnishing to an owner, lessee,

 

11  designee, or general contractor for improvements provided to a

 

12  residential structure.

 

13        Sec. 110. (1) A contractor who contracts to provide an

 

14  improvement to real property other than a residential structure

 

15  shall provide a sworn statement to the owner or lessee in each of

 

16  the following circumstances:

 

17        (a) When payment is due to the contractor from the owner or

 

18  lessee or when the contractor requests payment from the owner or

 

19  lessee.

 

20        (b) When a demand for the sworn statement has been made by

 

21  or on behalf of the owner or lessee.

 

22        (2) A subcontractor shall provide a sworn statement to the

 

23  owner or lessee when a demand for the sworn statement has been

 

24  made by or on behalf of the owner or lessee and the owner or

 

25  lessee has complied with the requirements of subsection (6).

 

26        (3) A subcontractor who has provided an improvement to real

 

27  property other than a residential structure shall provide a sworn


 

 1  statement to the contractor when payment is due to the

 

 2  subcontractor from the contractor or when the subcontractor

 

 3  requests payment from the contractor.

 

 4        (4) A sworn statement shall list each subcontractor and

 

 5  supplier with whom the person issuing the sworn statement has

 

 6  contracted relative to the improvement to the real property. The

 

 7  sworn statement shall contain a list of laborers with whom the

 

 8  person issuing the sworn statement has contracted relative to the

 

 9  improvement to the real property and for whom payment for wages

 

10  or fringe benefits and withholdings are due but unpaid and the

 

11  itemized amount of such wages or fringe benefits and

 

12  withholdings. The sworn statement shall be in substantially the

 

13  following form:

 

 

14                         SWORN STATEMENT

15 State of Michigan)

16                  )   ss.

17 County of .......)

18 ............(deponent), being sworn, states the following:

19 ................. is the (contractor) (subcontractor)

20 for an improvement to the following real property in

21 ................. County, Michigan, described as follows:

22 ...............................................................

23         (insert legal description of property)

 

 

24        The following is a statement of each subcontractor and

 

25  supplier, and laborer for whom payment of wages or fringe

 

26  benefits and withholdings is due but unpaid, with whom the

 

27  (contractor) (subcontractor) has (contracted) (subcontracted) for


 

 1  performance under the contract with the owner or lessee of the

 

 2  property, and the amounts due to the persons as of the date of

 

 3  this statement are correctly and fully set forth opposite their

 

 4  names:

 

 

  Name,

address,

  and

tele-

phone                                                        Amount

10 number                                                         of

11   of                                                         laborer

12 subcon-                                             Amount     fringe

13   trac-                                               of      benefits

14   tor,   Type of                           Balance  laborer      and

15   sup-   improve-  Total           Amount  to com-   wages      with-

16 plier,   ment      con-  Amount    cur-    plete     due     holdings

17   or      fur-     tract  already  rently   (op-      but    due but

18 laborer  nished    price   paid    owing   tional)   unpaid    unpaid

19 .....................................................................

20                                 Totals

21 (Some columns are not applicable to all persons listed)

 

 

22        The contractor has not procured material from, or

 

23  subcontracted with, any person other than those set forth and

 

24  owes no money for the improvement other than the sums set forth.

 

25        I make this statement as the (contractor) (subcontractor) or

 

26  as ......... of the (contractor) (subcontractor) to represent to

 

27  the owner or lessee of the property and his or her agents that

 

28  the property is free from claims of construction liens, or the

 

29  possibility of construction liens, except as specifically set

 

30  forth in this statement and except for claims of construction

 

31  liens by laborers that may be provided under section 109 of the

 

32  construction lien act, 1980 PA 497, MCL 570.1109.

 

33        WARNING TO OWNER OR LESSEE: AN OWNER OR LESSEE OF THE


 

 1  PROPERTY MAY NOT RELY ON THIS SWORN STATEMENT TO AVOID THE CLAIM

 

 2  OF A SUBCONTRACTOR, SUPPLIER, OR LABORER WHO HAS PROVIDED A

 

 3  NOTICE OF FURNISHING OR A LABORER WHO MAY PROVIDE A NOTICE OF

 

 4  FURNISHING UNDER SECTION 109 OF THE CONSTRUCTION LIEN ACT, 1980

 

 5  PA 497, MCL 570.1109, TO THE DESIGNEE OR TO THE OWNER OR LESSEE

 

 6  IF THE DESIGNEE IS NOT NAMED OR HAS DIED.

 

 7        ON RECEIPT OF THIS SWORN STATEMENT, THE OWNER OR LESSEE, OR

 

 8  THE OWNER'S OR LESSEE'S DESIGNEE, MUST GIVE NOTICE OF ITS

 

 9  RECEIPT, EITHER IN WRITING, BY TELEPHONE, OR PERSONALLY, TO EACH

 

10  SUBCONTRACTOR, SUPPLIER, AND LABORER WHO HAS PROVIDED A NOTICE OF

 

11  FURNISHING UNDER SECTION 109 OR, IF A NOTICE OF FURNISHING IS

 

12  EXCUSED UNDER SECTION 108, OR 108A, TO EACH SUBCONTRACTOR,

 

13  SUPPLIER, AND LABORER NAMED IN THE SWORN STATEMENT. IF A

 

14  SUBCONTRACTOR, SUPPLIER, OR LABORER WHO HAS PROVIDED A NOTICE OF

 

15  FURNISHING OR WHO IS NAMED IN THE SWORN STATEMENT MAKES A

 

16  REQUEST, THE OWNER, LESSEE, OR DESIGNEE SHALL PROVIDE THE

 

17  REQUESTER A COPY OF THE SWORN STATEMENT WITHIN 10 BUSINESS DAYS

 

18  AFTER RECEIVING THE REQUEST.

 

 

19                                 ....................................

20                                               Deponent

 

 

21        WARNING TO DEPONENT: A PERSON WHO GIVES A FALSE SWORN

 

22  STATEMENT WITH INTENT TO DEFRAUD IS SUBJECT TO CRIMINAL PENALTIES

 

23  AS PROVIDED IN SECTION 110 OF THE CONSTRUCTION LIEN ACT, 1980 PA

 

24  497, MCL 570.1110.

 

 

25 Subscribed and sworn to before me on ...............(DATE)


                        ...........................................

                         Notary Public,......... County, Michigan.

My commission expires: ........................... .

 

 

 4        (5) The contractor or subcontractor is not required to list

 

 5  in the sworn statement material furnished by the contractor or

 

 6  subcontractor out of his or her own inventory that was not

 

 7  purchased specifically for performing the contract.

 

 8        (6) On receipt of a sworn statement, the owner, lessee, or

 

 9  designee shall give notice of its receipt, either in writing, by

 

10  telephone, or personally, to each subcontractor, supplier, and

 

11  laborer who has provided a notice of furnishing under section 109

 

12  or, if a notice of furnishing is excused under section 108, or

 

13  108a, to each subcontractor, supplier, and laborer named in the

 

14  sworn statement. If a subcontractor, supplier, or laborer who has

 

15  provided a notice of furnishing or who is named in the sworn

 

16  statement makes a request, the owner, lessee, or designee shall

 

17  provide the requester a copy of the sworn statement within 10

 

18  business days after receiving the request.

 

19        (7) After the contractor or subcontractor provides the sworn

 

20  statement, the owner or lessee may withhold or, upon written

 

21  demand from the contractor, shall withhold from the amount due or

 

22  to become due to the contractor or to the subcontractor for work

 

23  already performed an amount sufficient to pay all sums due to

 

24  subcontractors, suppliers, or laborers, as shown by the sworn

 

25  statement, or due to lien claimants who have provided a notice of

 

26  furnishing under section 109. From the amount withheld, the owner

 

27  or lessee may directly pay subcontractors, suppliers, or laborers


 

 1  the amount they are due as shown by the sworn statement. If the

 

 2  contract provides for payments by the owner to the general

 

 3  contractor in the normal course of construction, but the owner

 

 4  elects to pay lien claimants directly under this section, the

 

 5  first time the owner elects to make payment directly to a lien

 

 6  claimant, he or she shall provide at least 5 business days'

 

 7  notice to the general contractor of the intention to make direct

 

 8  payment. Subsequent direct disbursements to lien claimants need

 

 9  not be preceded by the 5-day notice provided in this section

 

10  unless the owner first returns to the practice of paying all sums

 

11  to the general contractor. As between the owner or lessee and the

 

12  contractor or subcontractor, all payments made under this

 

13  subsection are considered the same as if paid directly to the

 

14  contractor or subcontractor. If an amount is withheld under this

 

15  subsection from the contractor or subcontractor, the owner or

 

16  lessee, upon request, shall prepare and provide to the contractor

 

17  or subcontractor an itemized statement of the sums withheld. If

 

18  an amount is paid directly to a lien claimant under this section,

 

19  the owner or lessee shall, if requested by the contractor or

 

20  subcontractor, provide to the contractor or subcontractor an

 

21  itemized statement of the sums paid.

 

22        (8) An owner, lessee, designee, mortgagee, or contractor may

 

23  rely on a sworn statement prepared by a party other than himself

 

24  or herself to avoid the claim of a subcontractor, supplier, or

 

25  laborer unless the subcontractor, supplier, or laborer has

 

26  provided a notice of furnishing as required under section 109 or

 

27  unless the notice of furnishing is excused under section 108. or


 

 1  108a.

 

 2        (9) If a contractor fails to provide a sworn statement to

 

 3  the owner or lessee before recording the contractor's claim of

 

 4  lien, the contractor's construction lien is not invalid. However,

 

 5  the contractor is not entitled to any payment, and a complaint,

 

 6  cross-claim, or counterclaim may not be filed to enforce the

 

 7  construction lien, until the sworn statement has been provided.

 

 8        (10) If a subcontractor fails to provide a sworn statement

 

 9  under subsection (2) to the owner or lessee before recording the

 

10  subcontractor's claim of lien, the subcontractor's construction

 

11  lien is valid. However, a complaint, cross-claim, or counterclaim

 

12  may not be filed to enforce the construction lien until the sworn

 

13  statement has been provided.

 

14        (11) A contractor or subcontractor who desires to draw money

 

15  and gives or causes to be given to any owner or lessee a sworn

 

16  statement required by this section that is false, with intent to

 

17  defraud, is guilty of a crime as follows:

 

18        (a) If the statement involved is for less than $200.00, the

 

19  contractor or subcontractor is guilty of a misdemeanor punishable

 

20  by imprisonment for not more than 93 days or a fine of not more

 

21  than $500.00 or 3 times the statement amount, whichever is

 

22  greater, or both imprisonment and a fine.

 

23        (b) If any of the following apply, the contractor or

 

24  subcontractor is guilty of a misdemeanor punishable by

 

25  imprisonment for not more than 1 year or a fine of not more than

 

26  $2,000.00 or 3 times the statement amount, whichever is greater,

 

27  or both imprisonment and a fine:


 

 1        (i) The statement involved is for $200.00 or more but less

 

 2  than $1,000.00.

 

 3        (ii) The statement involved is for less than $200.00 and the

 

 4  contractor or subcontractor has 1 or more prior convictions for

 

 5  committing or attempting to commit an offense under this act.

 

 6        (c) If any of the following apply, the contractor or

 

 7  subcontractor is guilty of a felony punishable by imprisonment

 

 8  for not more than 5 years or a fine of not more than $10,000.00

 

 9  or 3 times the statement amount, whichever is greater, or both

 

10  imprisonment and a fine:

 

11        (i) The statement involved is for $1,000.00 or more but less

 

12  than $20,000.00.

 

13        (ii) The statement involved is for more than $200.00 but less

 

14  than $1,000.00 and the contractor or subcontractor has 1 or more

 

15  prior convictions for violating or attempting to violate this

 

16  act. For purposes of this subparagraph, however, a prior

 

17  conviction does not include a conviction for a violation or

 

18  attempted violation described in subdivision (a) or (b)(ii).

 

19        (d) If any of the following apply, the contractor or

 

20  subcontractor is guilty of a felony punishable by imprisonment

 

21  for not more than 10 years or a fine of not more than $15,000.00

 

22  or 3 times the statement amount, whichever is greater, or both

 

23  imprisonment and a fine:

 

24        (i) The statement involved is for $20,000.00 or more.

 

25        (ii) The statement involved is for $1,000.00 or more but less

 

26  than $20,000.00 and the contractor or subcontractor has 2 or more

 

27  prior convictions for committing or attempting to commit an


 

 1  offense under this act. For purposes of this subparagraph,

 

 2  however, a prior conviction does not include a conviction for a

 

 3  violation or attempted violation described in subdivision (a) or

 

 4  (b)(ii).

 

 5        (12) For purposes of subsection (11), statements involved in

 

 6  separate incidents pursuant to a scheme or course of conduct

 

 7  within any 12-month period may be aggregated to determine the

 

 8  total amount involved in the statements.

 

 9        (13) If the prosecuting attorney intends to seek an enhanced

 

10  sentence for a violation under this section based upon the

 

11  defendant having 1 or more prior convictions, the prosecuting

 

12  attorney shall include in the complaint and information a

 

13  statement listing the prior conviction or convictions. The

 

14  existence of the defendant's prior conviction or convictions

 

15  shall be determined by the court, without a jury, at sentencing

 

16  or at a separate hearing for that purpose before sentencing. The

 

17  existence of a prior conviction may be established by any

 

18  evidence relevant for that purpose, including, but not limited

 

19  to, 1 or more of the following:

 

20        (a) A copy of the judgment of conviction.

 

21        (b) A transcript of a prior trial, plea-taking, or

 

22  sentencing.

 

23        (c) Information contained in a presentence report.

 

24        (d) The defendant's statement.

 

25        (14) If the sentence for a conviction under this section is

 

26  enhanced by 1 or more convictions, those prior convictions shall

 

27  not be used to further enhance the sentence for the conviction


 

 1  pursuant to section 10, 11, or 12 of chapter IX of the code of

 

 2  criminal procedure, 1927 PA 175, MCL 769.10, 769.11, and 769.12.

 

 3        (15) This section does not apply if the real estate involved

 

 4  is a residential structure. A contractor or subcontractor shall

 

 5  not provide a sworn statement to an owner or lessee for

 

 6  improvements provided to a residential structure.

 

 7        Sec. 115. (1) A person shall not require, as part of any

 

 8  contract for an improvement, that the right to a construction

 

 9  lien be waived in advance of work performed. A waiver obtained as

 

10  part of a contract for an improvement is contrary to public

 

11  policy, and shall be is invalid, except to the extent that

 

12  payment for labor and material furnished was actually made to the

 

13  person giving the waiver. Acceptance by a lien claimant of a

 

14  promissory note or other evidence of indebtedness from an owner,

 

15  lessee, or contractor shall does not of itself serve to waive or

 

16  discharge otherwise valid construction lien rights.

 

17        (2) A lien claimant who receives full payment for his or her

 

18  contract shall provide to the owner, lessee, or designee a full

 

19  unconditional waiver of lien.

 

20        (3) A lien claimant who receives partial payment for his or

 

21  her contract shall provide to the owner, lessee, or designee a

 

22  partial unconditional waiver of the lien for the amount which the

 

23  lien claimant has received, if the owner, lessee, or designee

 

24  requests the partial unconditional waiver.

 

25        (4) A partial conditional waiver of lien or a full

 

26  conditional waiver of lien shall be is effective upon payment of

 

27  the amount indicated in the waiver.


 

 1        (5) For purposes of this act, retainage that is not payable

 

 2  under a contract until the happening of a certain event in

 

 3  addition to the providing of an improvement is not due as of the

 

 4  date of the providing of the improvement is provided.

 

 5        (6) A waiver of a lien under this section shall be is

 

 6  effective when a person makes payment relying on the waiver

 

 7  unless at the time payment was made the person making the payment

 

 8  has written notice that the consideration for the waiver has

 

 9  failed.

 

10        (7) Subject to subsection (8), an owner, lessee, or designee

 

11  shall not rely on a full or partial unconditional or conditional

 

12  waiver of lien provided by a person other than the lien claimant

 

13  named in the waiver if the lien claimant has either filed a

 

14  notice of furnishing under section 109 or is excused from filing

 

15  a notice of furnishing under section 108 or 108a unless the

 

16  owner, lessee, or designee has first verified the authenticity of

 

17  the lien waiver with the lien claimant either in writing, by

 

18  telephone, or personally.

 

19        (8) An agent who is authorized to prepare and serve a notice

 

20  of furnishing or to prepare, record, and serve a claim of lien on

 

21  behalf of a laborer or group of laborers is automatically

 

22  authorized to provide and responsible for providing waivers of

 

23  lien, unless or until the laborer or group of laborers notifies

 

24  the designee in writing that someone other than the agent is

 

25  authorized to provide appropriate waivers. An individual laborer

 

26  may also provide waivers under this section instead of the agent.

 

27        (9) The following forms shall be used in substantially the


 

 1  following format to execute waivers of construction liens:

 

 

     (a)         PARTIAL UNCONDITIONAL WAIVER

I/we have a contract with ................................... to

                             (other contracting party)

provide .................... for the improvement to the property

described as .............................................., and

by signing this waiver waive my/our construction lien to the

amount of $ .............., for labor/materials provided

10 through ............................ .

11                     (date)

12

13 This waiver, together with all previous waivers, if any, (circle 

14 one)   does   does not   cover all amounts due to me/us for

15 contract improvement provided through the date shown above.

16

17 If the owner or lessee of the property or the owner's or lessee's

18 designee has received a notice of furnishing from me/one of us

19 or if I/we are not required to provide one, and the owner, lessee,

20 or designee has not received this waiver directly from me/one of

21 us, the owner, lessee, or designee may not rely upon it without

22 contacting me/one of us, either in writing, by telephone, or

23 personally, to verify that it is authentic.

24                                     ..............................

25                                     ..............................

26                                     (signature of lien claimant)

27

28 Signed on: ..............  Address:   ...........................

29               (date)              

30                                       ...........................

31                            Telephone: ...........................

32


       DO NOT SIGN BLANK OR INCOMPLETE FORMS. RETAIN A COPY.

     (b)         PARTIAL CONDITIONAL WAIVER

I/we have a contract with ...................................  to

                              (other contracting party)

provide .................... for the improvement to the property

described as: .............................................,  and

by signing this waiver waive my/our construction lien to the

10 amount of $ ............... , for labor/materials provided 

11 through................................ .

12                    (date)

13

14 This waiver, together with all previous waivers, if any,

15 (circle one)   does   does not   cover all amounts due to me/us

16 for contract improvement provided through the date shown above.

17 This waiver is conditioned on actual payment of the amount

18 shown above.

19

20 If the owner or lessee of the property or the owner's or lessee's

21 designee has received a notice of furnishing from me/one of us or

22 if I/we are not required to provide one, and the owner, lessee, or

23 designee has not received this waiver directly from me/one of us,

24 the owner, lessee, or designee may not rely upon it without

25 contacting me/one of us, either in writing, by telephone, or

26 personally, to verify that it is authentic.

27                                     ..............................

28                                     ..............................

29                                     (signature of lien claimant)

30

31 Signed on: ..............  Address:   ...........................

32                (date)               

33                                       ...........................


                           Telephone: ...........................

     DO NOT SIGN BLANK OR INCOMPLETE FORMS. RETAIN A COPY.

     (c)           FULL UNCONDITIONAL WAIVER

My/our contract with .........................................  to

                             (other contracting party)

provide ..................... for the improvement of the property

10 described as: .........................................   has been

11 fully paid and satisfied. By signing this waiver, all my/our

12 construction lien rights against the described property

13 are waived and released.

14

15 If the owner or lessee of the property or the owner's or lessee's

16 designee has received a notice of furnishing from me/one of us or

17 if I/we are not required to provide one, and the owner, lessee,

18 or designee has not received this waiver directly from me/one of

19 us, the owner, lessee, or designee may not rely upon it without

20 contacting me/one of us, either in writing, by telephone, or

21 personally, to verify that it is authentic.

22                                     ..............................

23                                     ..............................

24                                     (signature of lien claimant)

25

26 Signed on: ..............  Address:   ...........................

27                (date)               

28                                       ...........................

29                            Telephone:  ...........................

30

31      DO NOT SIGN BLANK OR INCOMPLETE FORMS. RETAIN A COPY.

32

33      (d)           FULL CONDITIONAL WAIVER


My/our contract with .........................................  to

                             (other contracting party)

provide ..................... for the improvement of the property

described as: ........................................   has been

fully paid and satisfied. By signing this waiver, all my/our

construction lien rights against the described property

are waived and released.

10 This waiver is conditioned on actual payment of ...............  .

11

12 If the owner or lessee of the property or the owner's or lessee's

13 designee has received a notice of furnishing from me/one of us or

14 if I/we are not required to provide one, and the owner, lessee,

15 or designee has not received this waiver directly from me/one of

16 us, the owner, lessee, or designee may not rely upon it without

17 contacting me/one of us, either in writing, by telephone, or

18 personally, to verify that it is authentic.

19                                     ..............................

20                                     ..............................

21                                     (signature of lien claimant)

22

23 Signed on: .............    Address:   ..........................

24               (date)              

25                                        ..........................

26                             Telephone:  ..........................

27

28      DO NOT SIGN BLANK OR INCOMPLETE FORMS. RETAIN A COPY.

 

 

29        Sec. 119. (1)  Except as otherwise provided by subsection

 

30  (4), as between parties entitled to claim construction liens

 

31  under this act, their claims of lien shall be treated as having

 

32  equal priority.


 

 1        (2) A construction lien under this act shall take takes

 

 2  priority over all garnishments for the contract debt made after

 

 3  commencement of the first actual physical improvement, without

 

 4  regard to the date of recording of the claim of lien is recorded.

 

 5        (3) A construction lien arising under this act shall take

 

 6  takes priority over all other interests, liens, or encumbrances

 

 7  which that may attach to the building, structure, or improvement,

 

 8  or upon the real property on which the building, structure, or

 

 9  improvement is erected, when if the other interests, liens, or

 

10  encumbrances are recorded subsequent to after the first actual

 

11  physical improvement.

 

12        (4) A mortgage, lien, encumbrance, or other interest

 

13  recorded before the first actual physical improvement to real

 

14  property shall have has priority over a construction lien arising

 

15  under this act. The priority of the mortgage shall exist exists

 

16  as to all obligations secured by the mortgage except for

 

17  indebtedness arising out of advances made subsequent to after the

 

18  first actual physical improvement. An advance made pursuant to

 

19  the mortgage, but subsequent to after the first actual physical

 

20  improvement shall have has priority over a construction lien if,

 

21  for that advance, the mortgagee has received a contractor's sworn

 

22  statement as provided in section 110, has made disbursements

 

23  pursuant to the contractor's sworn statement, and has received

 

24  waivers of lien from the contractor and all subcontractors,

 

25  laborers, and suppliers who have provided notices of furnishing.

 

26  The construction lien of any lien claimant not set forth on the

 

27  sworn statement upon which an advance was made shall be is


 

 1  subordinate to the lien of the mortgage, including the advance,

 

 2  unless prior to before the advance the lien claimant has provided

 

 3  the designee with a notice of furnishing if required by section

 

 4  109 or has recorded a claim of lien. Any advance made after a

 

 5  notice of furnishing has been provided or has been excused as

 

 6  provided in sections 108 , 108a, and 109 or a claim of lien has

 

 7  been recorded shall be is subordinate to the construction lien of

 

 8  that lien claimant unless prior to before the advance the

 

 9  mortgagee has received from that lien claimant either a full

 

10  unconditional waiver of lien or a partial unconditional waiver of

 

11  lien for the full amount due the lien claimant as of the date

 

12  through which the lien is waived as shown on the lien waiver and

 

13  the date through which the lien is waived as shown on the partial

 

14  unconditional waiver is within 30 days prior to before the

 

15  advance.

 

16        (5) For purposes of this section, retainage which that is

 

17  not payable under a contract until the happening of a certain

 

18  event in addition to the providing of an improvement , is not due

 

19  as of the date of the providing of the improvement is provided.

 

20        Sec. 203. (1) A claim of construction lien does not attach

 

21  to a residential structure, to the extent payments have been

 

22  made, if the owner or lessee files an affidavit with the court

 

23  indicating that the owner or lessee has done all of the

 

24  following:

 

25        (a) Paid the contractor for the improvement to the

 

26  residential structure according to the contract, indicating in

 

27  the affidavit the amount of the payment. The owner or lessee


 

 1  shall attach to the affidavit copies of the contract, any change

 

 2  orders, and any evidence of the payment that the owner or lessee

 

 3  has, including, but not limited to, a canceled check or a credit

 

 4  card or other receipt.

 

 5        (b) Not colluded with any person to obtain a payment from

 

 6  the fund.

 

 7        (c) Cooperated and will continue to cooperate with the

 

 8  department in the defense of the fund.

 

 9        (2) If there is no written contract as required by section

 

10  114, the filing of an affidavit under this section creates a

 

11  rebuttable presumption that the owner or lessee has paid the

 

12  contractor for the improvement. The presumption may be overcome

 

13  only by a showing of clear and convincing evidence to the

 

14  contrary.

 

15        (3) Subject to section 204, a person who has recorded a

 

16  claim of lien and who is precluded from having a construction

 

17  lien under subsection (1) may recover from the fund the amount he

 

18  or she would have been entitled to recover but for subsection

 

19  (1). A person who seeks recovery from the fund shall establish

 

20  all of the following:

 

21        (a) That he or she would be entitled to a construction lien

 

22  on a residential structure except for the defense provided in

 

23  subsection (1).

 

24        (b) That payment was made by the owner or lessee to the

 

25  contractor or subcontractor.

 

26        (c) That the contractor or subcontractor has retained or

 

27  used the proceeds or any part of the proceeds paid to the


 

 1  contractor or subcontractor without having paid the person

 

 2  claiming the construction lien.

 

 3        (d) That he or she has complied with section 201.

 

 4        (e) That he or she has not colluded with another person to

 

 5  obtain a payment from the fund.

 

 6        (f) That he or she has complied with any applicable

 

 7  licensing acts.

 

 8        (g) That he or she has made a reasonable effort to obtain

 

 9  payment from the contractor or subcontractor.

 

10        (h) That the contractor or subcontractor with whom the

 

11  person claiming the construction lien contracted is licensed if

 

12  required by law to be licensed.

 

13        (i) That the contractor or subcontractor with whom the

 

14  person claiming the construction lien contracted is the same

 

15  individual or legal entity with whom the owner or lessee

 

16  contracted.

 

17        (j) If the person claiming the construction lien is a

 

18  supplier, that he or she has documentary proof that, unless the

 

19  supplier had provided material or equipment to the contractor or

 

20  subcontractor within the preceding year, before he or she

 

21  provided the material or equipment that is the subject of the

 

22  lien without obtaining advance payment in full, he or she did

 

23  both of the following:

 

24        (i) Required the contractor or subcontractor to whom he or

 

25  she provided the material or equipment to complete and submit a

 

26  credit application.

 

27        (ii) Before beginning to supply material or equipment to the


 

 1  contractor or subcontractor without obtaining advance payment in

 

 2  full, did either of the following, as applicable:

 

 3        (A) If the contractor or subcontractor is a corporation

 

 4  whose shares are publicly traded, obtained a report on the

 

 5  contractor or subcontractor from a nationally or regionally

 

 6  recognized organization that provides credit ratings of

 

 7  businesses to determine the financial stability of the contractor

 

 8  or subcontractor.

 

 9        (B) If sub-subparagraph (A) does not apply, did both of the

 

10  following:

 

11        (I) Obtained a credit report on the owner or qualifying

 

12  officer or the principal partners, officers, shareholders, or

 

13  members of the contractor or subcontractor to determine the

 

14  financial stability of the contractor or subcontractor.

 

15        (II) If the contractor or subcontractor is less than 4 years

 

16  old, obtained a personal guaranty from the owner or 1 or more of

 

17  the partners, officers, directors, managing members, trustees, or

 

18  shareholders of the contractor or subcontractor.

 

19        (k) If the person claiming the construction lien is a

 

20  supplier seeking to recover for material or equipment supplied to

 

21  a contractor or subcontractor without obtaining advance payment

 

22  in full, that a credit report obtained by the supplier on the

 

23  contractor or subcontractor did not disclose any of the

 

24  following:

 

25        (i) That the contractor or subcontractor was, at the time of

 

26  the application, or had been, within 2 years before the

 

27  application, insolvent.


 

 1        (ii) That the contractor or subcontractor was, at the time of

 

 2  the application, subject to a receivership.

 

 3        (iii) Total delinquent judgments of more than $1,000.00.

 

 4        (4) A subcontractor, supplier, or laborer who seeks

 

 5  enforcement of a construction lien on a residential structure

 

 6  through foreclosure shall join the fund as a defendant in the

 

 7  foreclosure action within the period provided in section 117(1).

 

 8  The subcontractor, supplier, or laborer shall serve a summons and

 

 9  complaint on the office of the fund administrator within the

 

10  department by certified or registered mail or by leaving a copy

 

11  at the office. The failure to serve a summons and complaint under

 

12  this subsection bars recovery from the fund. After a defendant is

 

13  served with a summons and complaint in an action to foreclose a

 

14  construction lien, the department may intervene in the action as

 

15  a party defendant with respect to other construction liens.

 

16        (5) The attorney general shall make every reasonable effort

 

17  to defend the fund and may assert any defense to a claim of lien

 

18  that would have been available to the owner or lessee.

 

19        (6) A payment from the fund shall not include interest on

 

20  the unpaid principal amount due, including, but not limited to, a

 

21  time-price differential or a finance charge, that accrued after

 

22  90 days after the claim of lien was recorded.

 

23        (7) A payment from the fund to a supplier shall not include

 

24  money due for material or equipment supplied to a contractor or

 

25  subcontractor without obtaining advance payment in full if either

 

26  of the following applies:

 

27        (a) The contractor or subcontractor was delinquent in paying


 

 1  the supplier for material or equipment for more than the

 

 2  following number of 180 days after the first business day of the

 

 3  month following the shipment of the material or equipment. :

 

 4        (i) In 2007, 180 days.

 

 5        (ii) In 2008, 150 days.

 

 6        (iii) In 2009, 120 days.

 

 7        (iv) In 2010 and each year after 2010, 90 days.

 

 8        (b) The contractor or subcontractor was indebted to the

 

 9  supplier in an amount equal to or more than the credit limit

 

10  established by the supplier for the contractor or subcontractor

 

11  at the time the material or equipment was supplied.

 

12        (8) Payment from the fund shall be made only if the court

 

13  finds that a subcontractor, supplier, or laborer is entitled to

 

14  payment from the fund. Subject to section 204, after the judgment

 

15  has become final the department shall pay the amount of the

 

16  judgment out of the fund.