Analyst: Al Valenzio

Phone:  373-8080

Date:  April 12, 2005

SB 235 (S-1) FY 2004-05StateBuilding Authority Project Authorizations (as reported the House Appropriations Committee)

Executive Agreements

Senate

Passed

House Appropriations Comm.

GF/GP

Gross

GF/GP

Gross

GF/GP

Gross

Capital Outlay

$2,600

$2,600

$2,600

$2,600

$2,600

$2,600

FY 2004-05 Budgetary Issues:

Executive

Senate

House

CAPITAL OUTLAY

A.    State Agency, Community College, and University Planning Projects

The bill provides planning authorizations for 22 community college anduniversityStateBuilding Authority (SBA) projects as listed below.  This allows the institutions to hire professionals to develop a program statement and preliminary planning documents to more accurately identify project scope and cost.  These development costs are the responsibility of the respective institutions.  A planning authorization does not 'absolutely' guarantee State funding for an individual project.  It can, however be considered a solid State commitment for future funding.

 

1.  Alpena Community College

Planning authorization for the Instructional Addition/Renovation Project.  These projects are estimated to cost a combined $3,335,000 with the State share being $1,667,500.  Portions consist of both new construction and renovations to the ComputerTechnologyCenter and the Fine Arts program building.  Renovations will also be done to Natural and Biological Science laboratories.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

2.  Bay de Noc Community College

Planning authorization for the New West Campus Facility.  This project is estimated to cost $11,750,000 with the State share being $5,875,000 and consists of constructing a new instructional facility inDickinsonCounty,

Gross

GF/GP

$100

$100

$100

$100

$100

$100

3. Jackson Community College

Planning authorization for the Health Program Expansion and Information Commons Project.  These projects are estimated to cost a combined $15,000,000 with the State share being $7,500,000.  Project entails renovation of Whiting Hall to expand Nursing and other Health programs and construction of a newLearningResourceCenter.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

4. Lansing Community College

Planning authorization for the University Center Project.  This project is estimated to cost $10,000,000 with the State share being $5,000,000.  It entails construction of new building to house office and classroom space.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

5. Macomb Community College

Planning authorization for the Health Science and Technology Classroom Building Project.  This project is estimated to cost $12,000,000 with the State share being $6,000,000.  This entails construction of a new instructional facility.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

6. Mid-Michigan Community College

Planning authorization for the Science and Technology Center Project.  This project is estimated to cost $17,580,000 with the State share being $8,790,000.  This entails construction of a new instructional facility at theMt.Pleasant campus.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

7. Montcalm Community College

Planning authorization for the Life Science Training Facility.  This project consists of both new construction and renovation of existing space and is estimated to cost $6,000,000 with the State share being $3,000,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

8.  NorthwesternMichiganCollege

Planning authorization for the Oleson Center Renovations Project.  This classroom renovation/upgrade project is estimated to cost $1,310,000 with the State share being $655,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

9. Schoolcraft College

Planning authorization for the Technical Services Facility Project.  This project consists of both new construction and renovation of existing space and is estimated to cost $10,040,000 with the State share being $5,020,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

10.  SouthwesternMichiganCollege

Planning authorization for the Information Technology Center Renovations Project.  This project consists of both new construction and renovation of existing space and is estimated to cost $4,500,000 with the State share being $2,250,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

11. Washtenaw Community College

Planning authorization for the Technical and Industrial Building Renovations Project.  This classroom renovation/upgrade project is estimated to cost $7,185,000 with the State share being $3,000,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

12. West Shore Community College

Planning authorization for the New Student Learning Center Project.  This project is estimated to cost $7,912,000 with the State share being $3,956,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

13. Central Michigan University

Planning authorization for the Education Building Project.  This project consists of both new construction and renovation of existing space and is estimated to cost $50,000,000 with the State share being $37,500,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

14. Ferris State University

Planning authorization for the Instructional Resources Center Project.  This renovation project is estimated to cost $7,500,000 with the State share being $5,625,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

15. Grand Valley State University

Planning authorization for the Padnos College of Engineering Project.  ThisGrand Rapids campus project consists of both new construction and renovation of existing space and is estimated to cost $16,000,000 with the State share being $12,000,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

16. Michigan State University

Planning authorization for the Chemistry Building Renovations/Cooling Tower Project.  These projects are estimated to cost a combined $27,500,000 with the State share being $20,000,000.  TheChemistryBuilding project consists of both new construction and renovation of existing space.  Unrelated to this is the replacement of several cooling towers and related equipment that serve Erickson and Fee halls.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

17. Michigan Tech University

Planning authorization for the General Campus Renovations Project.  These major maintenance projects are estimated to cost a combined $10,000,000 with the State share being $7,500,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

18. Saginaw Valley State University

Planning authorization for the Pioneer Hall Renovations Project.  This project consists of both new construction and renovation of existing space and is estimated to cost $16,000,000 with the State share being $12,000,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

19. University of MichiganAnn Arbor

Planning authorization for the Student Activities Building/Observatory Lodge/Phoenix Memorial Lab Renovations projects.  These renovation projects are estimated to cost a combined $29,500,000 with the State share being $20,000,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

20. University of MichiganFlint

Planning authorization for the French Hall/Murchie Hall Renovations.  These renovation projects are estimated to cost a combined $9,350,000 with the State share being $7,000,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

21. Wayne State University

Planning authorization for the Engineering Development Center Project.  This building addition project is estimated to cost $26,500,000 with the State share being $15,000,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

22. Western Michigan University

Planning authorization for the Brown Hall Building Renovation Project.  This is estimated to cost $12,600,000 with the State share being $9,450,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

B. State Building Authority Financed Construction Projects

The bill provides cost and construction authorizations for the projects listed below.

 

1. Gogebic Community College

Cost and construction authorizations for Special Maintenance Projects.  The authorized project cost and State share is $1,000,000.  These funds will be used to address numerous minor and major building maintenance issues.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

2. Lake Superior State University

Cost and construction authorizations for Special Maintenance Projects.  The authorized project cost and State share is $163,100.  These funds will be used to address building maintenance issues.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

3.  Department of Management and Budget

Cost and construction authorizations for State Facility Preservation Projects, Phase I.  These funds will be used to address numerous State-owned building maintenance issues across the state, including theCapitolBuilding.  The authorized project cost and State share is $56,220,000.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

4.  Department of Information Technology

Cost and construction authorizations for Upgrades to the Public Safety Communications System.  The authorized project cost and State share is $13,780,000.  The Department of Information Technology owns and operates 181 radio tower sites across the state.  This project will allow for electronic and hardware upgrades at the tower sites and operations centers to improve communications and allow for additional local users to join.  Also, for security reasons, it's been determined that the tower atop the currently State-ownedDetroit Executive Plaza Building must be moved to a differentDetroit location.

Gross

GF/GP

$100

$100

$100

$100

$100

$100

FY 2004-05 Boilerplate Issues:

Executive

Senate

House

Sec.  206.  State Facility Preservation Projects

Establishes CapitolBuilding as first priority and lists projects to be funded under the line item authorization.

Included

Included

Included

Sec.  301. StateBuilding Authority

Allows for advances from the General Fund to meet construction cash flow needs for State agency projects.  Advances to be repaid, with interest, when the SBA issues debt.

Included

Included

Included

Sec.  302. StateBuilding Authority

University and community college facilities that collect revenues in excess of the facility's operational costs must be paid to the SBA to offset GF rent payments.

Included

Included

Included

Sec.  303. StateBuilding Authority

Provisions concerning SBA rent appropriations and paying insurance premiums on buildings financed by the SBA.

Included

Included

Included

Sec.  304. StateBuilding Authority

The SBA must issue a bonding/construction status report to the Legislature twice per year.

Included

Included

Included

Sec.  401.  Capital Outlay Processes, Procedures, and Reports

Projects authorized must comply with provisions of the DMB Act, PA 431 of 1984.

Included

Included

Included

Sec.  402.  Capital Outlay Processes, Procedures, and Reports

A statement of the facility's operating cost to be included with planning documents.

Included

Included

Included

Sec.  403.  Capital Outlay Processes, Procedures, and Reports

Administrative requirements between DMB and universities and community colleges.

Included

Included

Included

Sec.  406.  Capital Outlay Processes, Procedures, and Reports

Purpose, scope and total estimated cost of a project is not to be altered to meet matching funds requirement.

Included

Included

Included

Sec.  801. Community Colleges and Universities

Generally limits State support for a community college project to 50% of total project cost.  College matching funds are to be secured before construction can commence.

Included

Included

Included

Sec.  802. Community Colleges and Universities

State matching funds to be reduced proportionately as college and university funds decrease.

Included

Included

Included

Sec.  804. Community Colleges and Universities

Allows the State to have universities and community colleges document that they have their matching funds and governing board approval for the respective authorized project.

Included

Included

Included


SB 235 (S-1) - FY 2004-05 - State Building Authority Financed Capital Outlay Projects

Planning Authorizations

 

 Universities

Project

Total Est. Cost

State Share

School Share

% State

 Central

New Education Building

$50,000,000

$37,500,000

 $12,500,000

 75%

 Ferris

 Instructional Resource Center

7,500,000

5,625,000

 1,875,000

 75%

 Grand Valley

Padnos College of Engineering

16,000,000

12,000,000

 4,000,000

 75%

Michigan State

Chemistry Building/Cooling Tower

27,500,000

20,000,000

 7,500,000

 73%

Michigan Tech

General Campus Renovations

10,000,000

7,500,000

 2,500,000

 75%

 Saginaw Valley

Pioneer Hall Renovations

16,000,000

12,000,000

 4,000,000

 75%

 UM - AA

Stud. Activ./Observ. Lodge/Phoenix Lab

29,500,000

20,000,000

 9,500,000

 68%

 UM - Flint

French Hall/Murchie Hall

9,350,000

7,000,000

 2,350,000

 75%

 Wayne State

Engineering Development Center

26,500,000

15,000,000

 11,500,000

 57%

 Western

Brown Hall Renovations

12,600,000

9,450,000

3,150,000

 75%

 Subtotal Universities

$204,950,000

$146,075,000

$58,875,000

 71%

   Community Colleges

 Alpena

Instructional Addition/Renovation

$3,335,000

$1,667,500

 $1,667,500

 50%

 Bay De Noc

New West Campus Facility

11,750,000

5,875,000

 5,875,000

 50%

 Jackson

Health Program Expansion/Info. Com.

15,000,000

7,500,000

 7,500,000

 50%

 Lansing

University Center

10,000,000

5,000,000

 5,000,000

 50%

 Macomb

Health Science Technology Bldg

12,000,000

6,000,000

 6,000,000

 50%

Mid Michigan

Science and Technology Center

17,580,000

8,790,000

 8,790,000

 50%

 Montcalm

Life Science Training Facility

6,000,000

3,000,000

 3,000,000

 50%

 Northwestern

Oleson Center Renovation

1,310,000

655,000

 655,000

 50%

 Schoolcraft

Technical Services Facility

10,040,000

5,020,000

 5,020,000

 50%

 Southwestern

IT Instructional Center

4,500,000

2,250,000

 2,250,000

 50%

 Washtenaw

Technical and Industrial Bldg.

7,185,000

3,000,000

 4,185,000

 42%

 West Shore

Student Learning Center

7,912,000

3,956,000

3,956,000

50%

 Subtotal Community Colleges

$106,612,000

$52,713,500

$53,898,500

49%

Total Planning Authorizations

$311,562,000

$198,788,500

$112,773,500

Construction Authorizations

Tot. Auth. Cost

State Share

School Share

Lake Superior State

 Special Maintenance Projects

$163,100

$163,100

 $0

Gogebic CC

 Special Maintenance Projects

1,000,000

1,000,000

 0

State Agency Special Maintenance, Including Capitol Building

56,220,000

56,220,000

                             na

State Police Radio Towers Upgrade

13,780,000

13,780,000

                             na

Total Construction Authorizations

$71,163,100

$71,163,100

$0

Grand Total

$382,725,100

$269,951,600

$112,773,500